Our lift is available! Still to come: entrance ramp.
June 2026
Please enter from the Church Street side at the vestibule.
We are thrilled to announce that our lift is installed and operational! While we are still waiting on an updated vestibule and entrance ramp to be created, our new lift is complete, inspected, and ready for use...as are our brand-new bathrooms, including an accessible one. Please see the house staff if you need to use the lift and we will be happy to assist you!
We want to thank the Acton Community Preservation Committee, the residents of Acton who approved our funding at Acton Town Meeting, the Massachusetts Cultural Council(1), and the many Theatre III donors who have contributed towards it. This project would not be happening without all of your support.
Updated target date: we anticipate that this project will be completed by early summer 2026; check this page for updates.
(1) Funding for this project has been provided by the Massachusetts Cultural Facilities Fund, a program of the Commonwealth of Massachusetts, administered through a collaborative arrangement between MassDevelopment and the Mass Cultural Council.
December 9, 2025: the new bathrooms have drywall!
December 9, 2025: and the lower lift lobby has drywall!
November 10, 2025: view from the house to the boxed-in upper lift lobby.
November 10, 2025: inside the upper lift lobby at the back of audience left.
November 10, 2025: framing out the bathroom stalls, including the new accessible one on the right.
October 3, 2025: Building out the entrance to the lift in the downstairs lobby, cutting just into the former box-office-side restroom.
October 3, 2025: finding all sorts of old, out-of-date construction while rebuilding the restrooms on one side and adding an accessible one.
October 3, 2025: framing out the upstairs "lift lobby" that will exit onto the landing with a new entrance door into the auditorium.
September 18, 2025: The "London Bar" downstairs lobby is crammed with all the supplies we've pulled out of the concessions area, some of the bathroom supply closets, and our box office, as the initial work for the lift and accessible bathroom are underway.
September 18, 2025: The framing for our lift shaft is in place at the back of our risers in the auditorium.